“生態(tài)格網(wǎng)”堤坡防護(hù)技術(shù)施工規(guī)程l總則1.1生態(tài)格網(wǎng)防護(hù)工程是一種將多絞六角形格網(wǎng)片組裝成箱籠,并裝入塊石等填充料后,用作護(hù)岸的新技術(shù)。按結(jié)構(gòu)形式可以分為擋墻、護(hù)坡、護(hù)底、護(hù)腳、水下拋石籠等。習(xí)慣上又將護(hù)坡、護(hù)底工程上常用的較薄的一種箱籠稱(chēng)“生態(tài)格網(wǎng)”網(wǎng)墊(高度一般在17—30cm)。擋墻、拋石籠常用的較厚的一種稱(chēng)為“生態(tài)格網(wǎng)”網(wǎng)箱(一般高度在50cm以上)。治理山坡,綠化植被及水土保持常用的則稱(chēng)為“生態(tài)格網(wǎng)”掛網(wǎng)。“生態(tài)格網(wǎng)”網(wǎng)片系熱鍍鋅低碳鋼絲,或者鍍鋁鋅低碳鋼絲,也可以加涂樹(shù)脂保護(hù)膜后經(jīng)專(zhuān)用機(jī)械編織而成,視用途可組裝成所需要的形狀.1.2為規(guī)范“生態(tài)格網(wǎng)”箱籠的施工程序和施工技術(shù),確保工程施工質(zhì)量,不留隱患,達(dá)到設(shè)計(jì)規(guī)定的標(biāo)準(zhǔn),收到預(yù)期的工程與生態(tài)環(huán)境有機(jī)結(jié)合的效果,特制定本規(guī)程。1.3本規(guī)程依據(jù)《堤防工程施工規(guī)范》(sL260.98)制訂?!皅ualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
1生態(tài)格網(wǎng)”箱籠以及_相關(guān)的堤防工程施工,應(yīng)符合本規(guī)程的規(guī)定,本規(guī)程中未規(guī)定的應(yīng)符合《堤防工程施工規(guī)范》的規(guī)定和國(guó)家現(xiàn)行的有關(guān)標(biāo)準(zhǔn)的規(guī)定.2施工準(zhǔn)備2.1一般規(guī)定2.1.1施工單位開(kāi)工前,應(yīng)對(duì)合同或設(shè)計(jì)文件進(jìn)行深入研究,并應(yīng)編制施工組織設(shè)計(jì)。2.1.2應(yīng)根據(jù)水文氣象資料和工地實(shí)際情況,合理安排施工計(jì)劃。2.1.3開(kāi)工前,應(yīng)做好各項(xiàng)技術(shù)準(zhǔn)備工作,并做好“四通一平”、臨建工程等的準(zhǔn)備工作。2.2施工測(cè)量2.2.1施工單位必須根據(jù)設(shè)計(jì)文件,對(duì)有關(guān)數(shù)據(jù)、資料及施工圖中的幾何尺寸進(jìn)行檢驗(yàn)。2.2.2施工單位應(yīng)指定專(zhuān)人負(fù)責(zé)測(cè)量工作,并及時(shí)提供所需的測(cè)量資料。2.2.3施工測(cè)量的精度指標(biāo)應(yīng)符合以下要求:1平面位置允許誤差±30mm~±40mmqualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
22高程允許誤差_30mm--3坡面不平整度的相對(duì)高度差允許范圍30mm2.2.4施工中對(duì)借用或設(shè)置的施工控制標(biāo)志、高程點(diǎn),必須嚴(yán)加保護(hù),并定期檢測(cè)、校正.2.3機(jī)械、設(shè)備及材料準(zhǔn)備2.3.1旌工機(jī)械、施工工具、設(shè)備及材料的型號(hào)、規(guī)格、技術(shù)性能應(yīng)根據(jù)工程施工進(jìn)度和強(qiáng)度合理安排與調(diào)配.2.3.2根據(jù)工程施工進(jìn)度應(yīng)及時(shí)組織材料進(jìn)場(chǎng),并應(yīng)事先對(duì)原材料和半成品的質(zhì)量進(jìn)行檢驗(yàn)。2.3.3進(jìn)場(chǎng)原材料和半成品必須經(jīng)檢驗(yàn)合格后,方可使用。3旖工材料3.1“生態(tài)格網(wǎng)”網(wǎng)墊、“生態(tài)格網(wǎng)”網(wǎng)箱材料3.1.1“生態(tài)格網(wǎng)”網(wǎng)墊,“生態(tài)格網(wǎng)”網(wǎng)箱的材料為熱鍍鋅低碳鋼絲,或者鍍鋁鋅低碳鋼絲,也可以在此基礎(chǔ)上外涂樹(shù)脂保護(hù)膜。鋼絲材質(zhì)必須符合BS443,BS1052,GB\T700.1988標(biāo)準(zhǔn)規(guī)定。為保證鋼絲保護(hù)層涂料均勻并不受損傷,保證材料使用壽命,嚴(yán)禁使用多邊型或異型截面鋼絲。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
33.1.2“生態(tài)格網(wǎng)”網(wǎng)墊,“生態(tài)格網(wǎng)"網(wǎng)箱必須為由專(zhuān)用機(jī)械編織成的熱鍍鋅或鍍鋁鋅低碳鋼絲多絞六邊形格網(wǎng)片組裝而成,符合ASTMA97597標(biāo)準(zhǔn).3.1.3“生態(tài)格網(wǎng)”網(wǎng)片的網(wǎng)孔必須均勻,不得扭曲變形。網(wǎng)孔孔徑偏差應(yīng)小于設(shè)計(jì)孔徑的5%?!吧鷳B(tài)格網(wǎng)”網(wǎng)墊一般采用60x80mm網(wǎng)孑L基材,“生態(tài)格網(wǎng)”網(wǎng)箱一般采用80x100mm或者100x120mm網(wǎng)孔基材,符合ASTMA97597標(biāo)準(zhǔn)。3.1.4“生態(tài)格網(wǎng)"網(wǎng)片的抗壓、抗剪強(qiáng)度及有關(guān)力學(xué)指標(biāo)、耐腐蝕性必須達(dá)到設(shè)計(jì)要求,鋼絲的力學(xué)性能必須符合GB\T343.1994中的5_2條關(guān)于鍍鋅鋼絲的規(guī)定。3.1.5鋼絲與樹(shù)脂膜必須緊密結(jié)合。嚴(yán)禁采用多邊型或異型截面鋼絲材質(zhì),以保證涂膜均勻。3.1.6外涂樹(shù)脂膜的網(wǎng)片,涂膜質(zhì)量、厚度必須符合設(shè)計(jì)規(guī)定。涂膜材料抗拉強(qiáng)度應(yīng)不小于25MPa,斷裂伸長(zhǎng)率不低于180%。3.1.7“生態(tài)格網(wǎng)”網(wǎng)材必須有質(zhì)量保證書(shū)。3.2填充料qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
43.2.1填充料必須是堅(jiān)固密實(shí)、耐風(fēng)化好的石料.石料質(zhì)量應(yīng)符合《水利水電工程天然建筑材料勘察規(guī)程》(SDJl7.78)的規(guī)定。嚴(yán)禁使用風(fēng)化石。非裸露部分可以2適當(dāng)用廢砼碎塊或營(yíng)建廢料作為填充料。3.2.2填充石料(碎石或卵石)的粒徑,一般是網(wǎng)孔的1.5—2倍。3.2.3填充石料應(yīng)采用粒徑級(jí)配好的碎石或卵石.4“生態(tài)格網(wǎng)"護(hù)墊施工、4.1一般規(guī)定4.1.1“生態(tài)格網(wǎng)"網(wǎng)墊一般用作護(hù)坡或護(hù)底,首先按設(shè)計(jì)要求削坡并平整鋪設(shè)面,坡面或基底面應(yīng)平整、密實(shí)、無(wú)雜質(zhì).4.1.2現(xiàn)場(chǎng)如遇較差的地基土質(zhì)時(shí)(如遇流沙、淤泥等),應(yīng)另作地基處理后再鋪設(shè)護(hù)墊.4.1.3按設(shè)計(jì)要求鋪設(shè)防滲土工膜施工應(yīng)符合SL260.98標(biāo)準(zhǔn)的6.6條規(guī)定。4.1.4按設(shè)計(jì)要求鋪設(shè)土工織物或反濾層,其施工工序、質(zhì)量要求應(yīng)符合SL260—98標(biāo)準(zhǔn)的6.7條規(guī)定。4.2組裝“生態(tài)格網(wǎng)”網(wǎng)墊qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
54.2.1間隔網(wǎng)與網(wǎng)身應(yīng)成90℃相交后,才可綁扎成護(hù)墊狀.4.2.2綁扎線必須是與網(wǎng)線同材質(zhì)的鋼絲.4.2.3每道綁扎必須是雙股線并絞緊。4.2.4網(wǎng)墊組的間隔網(wǎng)與網(wǎng)身間綁扎道數(shù)必須符合以下要求:1間隔網(wǎng)與網(wǎng)身的四處交角各綁扎一道;2間隔網(wǎng)與網(wǎng)身交接處,每間隔20cm綁扎一道.4.2.5網(wǎng)墊組必須按設(shè)計(jì)圖示位置依次安放到位。4.2.6網(wǎng)墊組間相鄰的上下框線或折線,必須符合每間隔20cm綁扎一道要求。4.3填充石料施工4.3.1石料規(guī)格質(zhì)量必須符合設(shè)計(jì)要求。4.3.2同時(shí)均勻的向一組護(hù)墊的各網(wǎng)格內(nèi)填入石料,嚴(yán)禁往單個(gè)網(wǎng)格內(nèi)填入石料。4.3.3填充石料可一次填滿(mǎn)高度,填充石料項(xiàng)面宜適當(dāng)高出網(wǎng)墊3.5cm,必須密實(shí)。4.3.4填充石料的容重應(yīng)達(dá)到1。70T/M3.4.3.5裸露的填充石料,表面應(yīng)以人工或機(jī)械砌壘整平,石料間相互搭接.4.4封蓋施工4.4.1面層石料必須砌壘整平.4.4.2封蓋網(wǎng)與網(wǎng)身、間隔網(wǎng)間相交邊框線必須每間隔20cm綁扎一道。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
64.4.3應(yīng)將所有網(wǎng)墊組相鄰的封蓋框線與邊框線綁扎在一起。5“生態(tài)格網(wǎng)”網(wǎng)箱施工5.1一般規(guī)定5.1.1“生態(tài)格網(wǎng)"網(wǎng)箱擋墻的基底土質(zhì)及其密實(shí)度,基礎(chǔ)網(wǎng)箱入土深度和輪廓線長(zhǎng)度及寬度,均應(yīng)符合設(shè)計(jì)要求。5.1.2現(xiàn)場(chǎng)如遇較差的地基土質(zhì)時(shí),應(yīng)另作地基處理,處理后的地基承載力必須符合設(shè)計(jì)要求.5.1.3按設(shè)計(jì)要求鋪設(shè)防滲土工膜施工,應(yīng)符合sL260.98標(biāo)準(zhǔn)6.6條規(guī)定.5.1.4按設(shè)計(jì)要求鋪設(shè)土工織物或反濾層施工,應(yīng)符合sL260.98標(biāo)準(zhǔn)6.7條規(guī)定。5.1.5“生態(tài)格網(wǎng)”網(wǎng)箱砌體應(yīng)符合下列要求:1網(wǎng)箱組砌體平面位置必須符合設(shè)計(jì)圖紙要求;2網(wǎng)箱層與層間砌體應(yīng)縱橫交錯(cuò),上下聯(lián)結(jié),嚴(yán)禁出現(xiàn)“通縫”;3每層網(wǎng)箱組均應(yīng)適當(dāng)放置“丁”字箱體。4砌體外露面應(yīng)平整美觀.5.1.6“生態(tài)格網(wǎng)”網(wǎng)箱擋墻墻后還土宜分層夯實(shí),每層還土厚度宜控制在20cm左右。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
75.2組裝“生態(tài)格網(wǎng)”網(wǎng)箱5.2.1間隔網(wǎng)與網(wǎng)身應(yīng)成90℃相交,經(jīng)綁扎形成長(zhǎng)方形或正方形網(wǎng)箱組或網(wǎng)箱.5.2.2綁扎線必須是與網(wǎng)線同材質(zhì)的鋼絲。5.2.3每一道綁扎必須是雙股線并絞緊。5.2.4構(gòu)成網(wǎng)箱組或網(wǎng)箱的各種網(wǎng)片交接處綁扎道數(shù)應(yīng)符合以下要求:1間隔網(wǎng)與網(wǎng)身的四處交角各綁扎一道;2間隔網(wǎng)與網(wǎng)身交接處每間隔20cm綁扎一道;3間隔網(wǎng)與網(wǎng)身間的相鄰框線,必須采用組合線聯(lián)結(jié),即用綁扎線一孔繞。一圈接一孔繞二圈呈螺旋狀穿孔絞繞聯(lián)結(jié).5.2.5網(wǎng)箱組間連接綁扎,應(yīng)符合下列要求:l相鄰網(wǎng)箱組的上下四角各綁扎一道;2相鄰網(wǎng)箱組的上下框線或折線,必須每間隔20cm綁扎一道:3相鄰網(wǎng)箱組的網(wǎng)片結(jié)合面則每平米綁扎2處:4在綁扎相鄰邊框線下角一道時(shí),如下方有網(wǎng)箱組,必須將下方網(wǎng)箱一并綁扎,以求連成一體;5.2.6裸露部位的網(wǎng)片,應(yīng)在每次箱內(nèi)填石1/3高后設(shè)置拉筋線。45.3填充石料施工5.3.1填充“生態(tài)格網(wǎng)"網(wǎng)箱的石料規(guī)格質(zhì)量,必須符合設(shè)計(jì)要求。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
8532必須同時(shí)均勻地向同層的各箱格內(nèi)投料,嚴(yán)禁將單格網(wǎng)箱一次性投滿(mǎn)。5.3.3填料施工中,應(yīng)控制每層投料厚度在30cm以下,一般一米高網(wǎng)箱分四層投料為宜.5.3.4填充石料頂面宜適當(dāng)高出網(wǎng)箱3.5cm且必須密實(shí)。5.3.5填充石料容重應(yīng)達(dá)1.70T/M3。5.3.6裸露的填充石料,表面應(yīng)以人工或機(jī)械砌壘整平,石料問(wèn)應(yīng)相互搭接.5.4箱體封蓋施工5.4.1封蓋必須在頂部石料砌壘平整的基礎(chǔ)上進(jìn)行。5.4.2必須先使用封蓋夾固定每端相鄰結(jié)點(diǎn)后,再加以綁扎。5.4.3封蓋與網(wǎng)箱邊框相交線,應(yīng)每間隔20cm綁扎一道。5.4.4每層“生態(tài)格網(wǎng)”網(wǎng)箱的施工步驟按5.2~5.4條進(jìn)行.5.4.5用作拋石籠的“生態(tài)格網(wǎng)”網(wǎng)箱或網(wǎng)箱組,制作程序應(yīng)按5.2~5.4條進(jìn)行。5.5箱體植被施工5.5.1依土壤、氣候和景觀要求,做好植被草種或灌木的選擇.5.5.2網(wǎng)箱封蓋后,空隙處宜填滿(mǎn)壤土,頂部填滿(mǎn)高約5cm壤土.5.5.3植被的后期養(yǎng)護(hù)宜依據(jù)草種或灌木的特性而定。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
96質(zhì)量控制6.1一般規(guī)定6.1.1旌工單位應(yīng)建立健全完善的質(zhì)量保證體系,建設(shè)、監(jiān)理單位應(yīng)建立相應(yīng)的質(zhì)量檢查體系,分別承擔(dān)工程質(zhì)量的自檢和抽檢任務(wù),實(shí)行全面質(zhì)量管理.6·1.2工程質(zhì)量檢測(cè)人員所需資質(zhì)條件以及工程質(zhì)量檢驗(yàn)的職責(zé)范圍、工作程序、事故處理、數(shù)據(jù)處理等要求,均應(yīng)符合《水利水電工程施工質(zhì)量評(píng)定規(guī)程(試行)》(SLl76—1996)的規(guī)定。6·1·3應(yīng)保證檢測(cè)成果、材料檢驗(yàn)資料的真實(shí)性,嚴(yán)禁偽造或任意舍棄成果和資料;質(zhì)量檢測(cè)記錄應(yīng)妥善保存,嚴(yán)禁涂改或自行銷(xiāo)毀。6·1.4“生態(tài)格網(wǎng)"防護(hù)工程施工質(zhì)量應(yīng)包括內(nèi)在質(zhì)量和外觀質(zhì)量。6.1.5必須在每一道工序進(jìn)行自檢、抽檢合格后,方可繼續(xù)下道工序。6·1·6質(zhì)量檢測(cè)部位應(yīng)有代表性,且應(yīng)在面上均勻分布,不得隨意挑選。6.1.7隱蔽工程應(yīng)會(huì)同監(jiān)理一起檢驗(yàn),或拍照留底.56.2材料質(zhì)量控制6.2.1“生態(tài)格網(wǎng)”網(wǎng)材的規(guī)格質(zhì)量應(yīng)重點(diǎn)檢查下列內(nèi)容:l用于編織“生態(tài)格網(wǎng)”箱籠的材料的化學(xué)性能、力學(xué)指標(biāo)是否符合設(shè)計(jì)要求;qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
102網(wǎng)孔孔徑是否符合3.1_3條要求;3外涂樹(shù)脂薄膜質(zhì)量是否符合3.1.5條要求.6.2.2填充石料的質(zhì)量及規(guī)格應(yīng)重點(diǎn)檢查下列內(nèi)容:1石料質(zhì)量是否符合3.2.1條規(guī)定;2石料粒徑是否符合3.2_2條規(guī)定。6.2.3土工織物的質(zhì)量控制,應(yīng)重點(diǎn)檢查下列內(nèi)容:1透水土工織物的質(zhì)量和規(guī)格是否符合設(shè)計(jì)要求;2防滲土工織物的質(zhì)量和規(guī)格是否符合設(shè)計(jì)要求.6.3“生態(tài)格網(wǎng)”網(wǎng)墊施工質(zhì)量控制6.3.1鋪設(shè)網(wǎng)墊的坡面、鋪設(shè)面的平整度、土體密實(shí)度是否符合設(shè)計(jì)要求。6.3.2檢驗(yàn)坡面、鋪設(shè)面的平面位置、高程是否符合設(shè)計(jì)要求.6.3.3檢查反濾層、防滲土工膜的施工是否符合4.1—3及4.1.4條規(guī)定.6.3.4檢查護(hù)墊組拼裝工序、工藝是否符合4.2條規(guī)定。6.3.5檢查護(hù)墊幾何尺寸是否符合下列要求:1高度(H)允許偏差:±lO%:2寬度(B)允許偏差:±3%;3長(zhǎng)度(L)允許偏差:±3%。6.3.6檢查填充石料的旋工程序、旌工工藝是否符合4—3條規(guī)定。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
116.3.7抽查護(hù)墊面層平整度是否符合高差〈3cm的規(guī)定。6.3.8單元工程劃分,每500m。左右劃分為一個(gè)單元。6.4“生態(tài)格網(wǎng)”網(wǎng)箱施工質(zhì)量控制6.4.1檢驗(yàn)“生態(tài)格網(wǎng)"網(wǎng)箱擋墻基礎(chǔ)土質(zhì)、基坑尺寸、高程、位置是否符合設(shè)計(jì)要求。6.4.2需地基處理的,檢驗(yàn)地基承載力是否滿(mǎn)足要求。6.4.3檢查網(wǎng)箱組拼裝工藝、拼裝程序是否符合5.2條規(guī)定。6.4.4抽檢網(wǎng)箱組幾何尺寸是否符合下列要求:l高度(H)允許偏差±5%;2寬度(B)允許偏差±3%;3長(zhǎng)度(L)允許偏差±3%;6.4.5檢查填充石料施工工藝、程序是否符合5_3條規(guī)定。66.4.6抽查網(wǎng)箱擋墻墻面平整度是否符合允許偏差~<5cm的要求。6.4.7檢驗(yàn)網(wǎng)箱擋墻垂直度是否滿(mǎn)足傾斜度≤O.5%的要求.6.4.8檢查墻后還土施工工藝是否符合5.1.6條規(guī)定。6.4.9檢查反濾層、防滲土工膜的施工質(zhì)量是否符合4.1.3及4.1.4條規(guī)定.6.4.10單元工程劃分,每100m左右長(zhǎng)墻身劃分為一個(gè)單元。7工程驗(yàn)收7.1“生態(tài)格網(wǎng)”qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould
12護(hù)岸工程驗(yàn)收可劃分為分部工程驗(yàn)收和竣工驗(yàn)收兩個(gè)階段。驗(yàn)收組或驗(yàn)收委員會(huì)的組成按《水利水電建設(shè)工程驗(yàn)收規(guī)程》的要求進(jìn)行.7.2分部工程完成后應(yīng)及時(shí)進(jìn)行驗(yàn)收。隱蔽工程驗(yàn)收可分段進(jìn)行,完工一段驗(yàn)收一段。前道工序未經(jīng)驗(yàn)收,施工單位不得進(jìn)行下一道工序施工.7.3分部工程驗(yàn)收的圖紙,資料和成果應(yīng)按竣工驗(yàn)收的標(biāo)準(zhǔn)制備。7.4工程完工后,施工單位必須提交經(jīng)工地負(fù)責(zé)人簽署的下列文件和資料:l竣工圖紙;2施工中有關(guān)變更的說(shuō)明和記錄:3單元工程質(zhì)量評(píng)定表;4隱蔽工程檢查記錄,照片或攝像資料;5質(zhì)量事故記錄分析資料及處理結(jié)果;6施工單位的試驗(yàn)、測(cè)量原始資料及主要材料的質(zhì)保書(shū)和抽樣檢驗(yàn)資料;7施工單位的工程質(zhì)量自檢報(bào)告;8施工總結(jié)報(bào)告和清單;9施工大事記。7.5竣工驗(yàn)收合格后,應(yīng)將所有資料整理成冊(cè),移交管理單位,并抄報(bào)有關(guān)部門(mén)備查。qualified,finishedfixed.(4)thenecessaryconstructionequipmentconfigurationsareinplace,constructionworkersarrivedatthescene,holdingavalidworkpermitandcertificateofthecorrespondingtype.(5)theconstructionplanapproval,constructiontechnologytogivethelow-downtheworkhasbeencompleted.(6)enterthesiteinspectionofpipes,pipefittings,valvesandothercomprehensive.Pipes,pipesurfaceshallbefreeofcracks,scars,porosity,slag,folds,severecorrosionandotherdefects,openingandcloseflexibly,maintenanceofhighpressurevalvesoneatastrengthandtightnesstest,passtheinspection,testpipes,valvescleantheclosedlogo,placedneatlyinthespecifiedlocation.(7)enterthesceneofthepipelinecomponents,preformsaredesignedaccordingtotheirdocumentationrequirements,themodels,specifications,material,quantitycheck.(8)thepipelineofhighpressurepipeprefabricationfactoryintothescene,shouldcontrolone-linediagram,checkbytheirspecifications,sizes,materialsandtrends.1.2....,Itisimportanttoensurecorrectsizeandsurfaceroughness.Nomatterwhichmethodofcutting,withanglegrindercuttingsurfaceoxide,dross,ruggedandBurrBurrandGrind.(2)theincisionqualityshallconformtothefollowingprovisionsofthepipe:cutsurfacesshouldbesmooth,freefromcracks,heavyleather,Burr,bump,necking,dross,ferrousoxide,iron,etc.Cutsideslopedeviationshouldnotexceed1%oftheoutsidediameterofthepipe,andmustnotexceed3mm.1.2.4thepipinginstallation(1)afterinstallingtheorderprincipleisthefirstlarge-caliber,small-bore,highfirst,thentheground,OutdoorIndoor,headafterthefirstpipe,andpipemovingdeviceconnection,preferablyfromthedevicetotheexternalpiping,pipingandpipelineinstallationsynchronization.(2)prefabricatedpiping,pipeline,andthepipelineshould