常減壓裝置拆除施工方案

常減壓裝置拆除施工方案

ID:22336422

大?。?07.00 KB

頁(yè)數(shù):10頁(yè)

時(shí)間:2018-10-28

常減壓裝置拆除施工方案_第1頁(yè)
常減壓裝置拆除施工方案_第2頁(yè)
常減壓裝置拆除施工方案_第3頁(yè)
常減壓裝置拆除施工方案_第4頁(yè)
常減壓裝置拆除施工方案_第5頁(yè)
資源描述:

《常減壓裝置拆除施工方案》由會(huì)員上傳分享,免費(fèi)在線閱讀,更多相關(guān)內(nèi)容在行業(yè)資料-天天文庫(kù)。

1、中海石油東營(yíng)石化有限公司7萬噸/年常減壓裝置拆除施工方案工程名稱:7萬噸/年常減壓裝置拆除工程工程地點(diǎn):中海石油東營(yíng)石化廠區(qū)編制單位:生產(chǎn)技術(shù)部編制:編制日期:年月日審核:審核日期:年月日批準(zhǔn):批準(zhǔn)日期:年月日第10頁(yè)共10頁(yè)目錄一、工程概況······························································3二、主要施工內(nèi)容·························································3三、編制依據(jù)···········

2、···················································3四、人員組織······························································3五、施工要求·····························································4六、施工進(jìn)度表··························································5七、拆除施工方式····

3、······················第10頁(yè)共10頁(yè)·······························67.1、施工方法····························································67.1.1、設(shè)備、儲(chǔ)罐及管道置換及清理·····································67.1.2、管道拆除··························································67.1.3、燃料油罐

4、拆除·····················································67.1.4、外保溫的拆除·····················································67.1.5、吊卸·······························································67.1.6、現(xiàn)場(chǎng)清理··························································7第10頁(yè)

5、共10頁(yè)八、現(xiàn)場(chǎng)施工安全及防護(hù)措施·············································7一、工程概況根據(jù)中海石油煉化有限責(zé)任公司【海油煉化財(cái)[2013]268號(hào)】文件要求,中海石油東營(yíng)石化有限公司決定于2014年3月對(duì)7萬噸/年常減壓裝置進(jìn)行拆除工作。二、主要施工內(nèi)容:1、7萬噸/年常減壓裝置管廊上部約930米工藝管道,一個(gè)燃料油罐;2、裝置區(qū)管廊支架;3、兩臺(tái)真空泵、兩個(gè)水冷槽、常爐龍門架及空冷平臺(tái);4、工藝平臺(tái)及兩塔附屬管線。三、編制依據(jù)1、《石油化工劇毒、可燃介質(zhì)管道工程施工及驗(yàn)收規(guī)范

6、》SH3501-20022、《現(xiàn)場(chǎng)設(shè)備、工藝管道焊接工程施工及驗(yàn)收規(guī)范》GB50236-983、《工業(yè)金屬管道工程施工及驗(yàn)收規(guī)范》GB50235-974、《石油化工施工安全技術(shù)規(guī)定》SH3505-20045、《石油化工靜電接地設(shè)計(jì)規(guī)范》SH3097-20006、《中海石油東營(yíng)石化有限公司QHSE管理制度》四、人員組織為確保7萬噸/年常減壓裝置安全拆除,達(dá)到“有組織、有計(jì)劃,有方案”施工,成立中海石油東營(yíng)石化有限公司7萬噸/年常減壓裝置拆除領(lǐng)導(dǎo)小組。組長(zhǎng):韓祚平第10頁(yè)共10頁(yè)副組長(zhǎng):李德錄小組成員:趙樹梁、張文光、榮愛民、禹建福

7、領(lǐng)導(dǎo)小組下設(shè)3個(gè)專業(yè)組:(1)工藝排查組:組長(zhǎng):榮愛民組員:季善義、吳愛峰工藝排查組職責(zé):負(fù)責(zé)對(duì)7萬噸/年常減壓裝置危險(xiǎn)源摸底排查,現(xiàn)場(chǎng)確認(rèn)每天達(dá)到施工條件的工作量。(2)安全監(jiān)管組:組長(zhǎng):趙樹梁組員:張紅兵、武玉強(qiáng)、劉相偉安全監(jiān)管組職責(zé):負(fù)責(zé)現(xiàn)場(chǎng)各項(xiàng)安全監(jiān)管及應(yīng)急事故處理。(3)現(xiàn)場(chǎng)施工組:組長(zhǎng):張文光組員:禹建福、劉宇、藺志偉現(xiàn)場(chǎng)管理組職責(zé):負(fù)責(zé)施工方案確定與現(xiàn)場(chǎng)施工安全及進(jìn)度管理,保證拆除工作有序開展。五、施工要求1、本工程的施工區(qū)域位于油品罐區(qū)東側(cè),維修中心焊工班南側(cè),且周邊有各種施工剩余材料,現(xiàn)場(chǎng)條件相對(duì)復(fù)雜,在施工過

8、程中要嚴(yán)格按照拆除方案進(jìn)行施工。2、施工期間嚴(yán)格按照“以人為本,安全第一”理念,從外圍慢慢向內(nèi)部滲透,按照計(jì)劃進(jìn)行拆除。3、在拆除過程中由于施工場(chǎng)地面積較小應(yīng)隨拆隨清,防止廢料堆積影響施工進(jìn)度。4、根據(jù)施工組織人員分配,在施工過程中需遵循以下幾點(diǎn)要求:(1)施工

當(dāng)前文檔最多預(yù)覽五頁(yè),下載文檔查看全文

此文檔下載收益歸作者所有

當(dāng)前文檔最多預(yù)覽五頁(yè),下載文檔查看全文
溫馨提示:
1. 部分包含數(shù)學(xué)公式或PPT動(dòng)畫的文件,查看預(yù)覽時(shí)可能會(huì)顯示錯(cuò)亂或異常,文件下載后無此問題,請(qǐng)放心下載。
2. 本文檔由用戶上傳,版權(quán)歸屬用戶,天天文庫(kù)負(fù)責(zé)整理代發(fā)布。如果您對(duì)本文檔版權(quán)有爭(zhēng)議請(qǐng)及時(shí)聯(lián)系客服。
3. 下載前請(qǐng)仔細(xì)閱讀文檔內(nèi)容,確認(rèn)文檔內(nèi)容符合您的需求后進(jìn)行下載,若出現(xiàn)內(nèi)容與標(biāo)題不符可向本站投訴處理。
4. 下載文檔時(shí)可能由于網(wǎng)絡(luò)波動(dòng)等原因無法下載或下載錯(cuò)誤,付費(fèi)完成后未能成功下載的用戶請(qǐng)聯(lián)系客服處理。